COLWALL PARISH COUNCIL
Minutes of the Assembly of the Parish Meeting duly convened and held at
the Colwall C of E Primary School, Colwall Green, Colwall on Wednesday 27th
February 2008.
1. Welcome and
apologies for absence.
The Chairman, Mrs Nicky Carless welcomed circa 100 members of the Public,
10 members of the Parish Council,
3 representatives of Network Rail – Chris Mair –Public Affairs, Mike Smith – Structural Engineer and Ian Fostic - Engineer and
3 representatives of Herefordshire Council – Cabinate Member - Councillor Brian Wilcox, Martin Jackson and Michael Hayes.
Also present were Herefordshire Councillor Roy Stockton and Councillor Rees Mills
Apologies had been received from Councillors Mills and Morris
2. Report received from Herefordshire Council and Network Rail regarding
Colwall Green Railway Bridge
Representatives of Network Rail and
Herefordshire Council were invited to explain the proposals as set out in
Progress Report no 5, the rationale behind the proposals and the timetable when
this information is developed.
Herefordshire Council
provided a detailed breakdown of the timetable of events that they had
undertaken since the bridge closure in August 2007.
Network Rail provided a
timetable for the replacement bridge. The highlight of this report was that the
timetable for the new bridge has been shortened by the normal 3 year timetable
to 12/13 months from February 2008. Detailed engineering reports, which have
been compiled since the bridge closure in August 2007, have given Network Rail
sufficient information to enable them to provide the timetable presented, which
indicates the replacement bridge should be open to all traffic by the end of
March 2009.
A further detailed
progress report, produced jointly from Herefordshire Council and Network Rail,
is due the week commencing 3rd March 2008. This will provide details
of the works and will include a written statement confirming both parties
committement to delivering within the timescale set, and confirming the funds
are in place to deliver within the timescale detailed.
It was AGREED the Clerk will liaise with the
emergency services over concerns about access to the Village if the road is
closed in Upper Colwall, taking into account the current vehicle restrictions
over the Bridge
3. Parishioners Question Time.
Numerous questions
were asked and answered regarding the facts presented.
Should any
parishioners not be able to access the monthly progress reports via the Parish
Council’s website or the Village Notice Boards, these can be requested direct
from Herefordshire Council by calling 01432 261800,
or emailing streets@herefordshire.gov.uk
or by writing to
Herefordshire Council, Highways and Transportation Department, Unit 3, Thorn
Business Park, Rotherwas, Hereford HR2 6JT.
The meeting closed
at 8.45 p.m.