Colwall Green Railway Bridge

 

Report 11 on progress leading towards the re-opening of the bridge

Highway layout over the bridge

The initial highway layout over the bridge proposed in progress report 7 (issued April 2008) consisted of a 4.5m carriageway for single way traffic and traffic signals, a 1.7m footway and a 3.0 m footway (now without a dedicated cycleway), all within the width of the existing highway. Following discussions with representatives of Colwall Parish Council there was a request to consider an alternative layout with two vehicle lanes over the bridge.

As stated in report 10 in view of the strong concerns that have been expressed and the permanent nature of the work deliberations on the layout have sought to ensure that the decision made will be the correct one giving consideration to all the relevant factors related to safety issues, traffic flows and the environmental aspects of the site.

Herefordshire Council seeks to provide Colwall with a bridge within a network that provides an efficient traffic flow without prejudice to the safety issues particularly of non-motorists. In order to meet these aspirations a fully detailed investigation and report was commissioned and subsequently presented by the Director of Environment and Culture to the Cabinet Member for Highways and Transportation on 4 February 2009.

 

In the report two highway options were considered namely:

·         Single way – traffic controlled working across the bridge with widened footways

·         Two way – narrowing of carriageway providing widened footways

The Parish Council, through their consultant, had also submitted proposals for two way operation that have been reviewed.

The report recommended that having considered the benefits and disbenefits of both two way and single way arrangements (including options proposed by Parish Council), a single way traffic controlled option across the bridge is adopted and this has been up held by the Cabinet Member for Highways and Transportation

 

Reasons given in the report for the recommendation were:

 

·               To ensure appropriate highway layout taking into account the design constraints and safety.

·               Single way traffic control across the bridge will remove any risk of vehicle conflict associated with the two way option allowing localised improvements for non motorised users.

·               Two way options were considered (both Council design and options submitted by Parish Council) but were be discounted due to the significant risk of vehicle conflict and accidents they introduce onto network.

 

An associated benefit would be that in overall terms, average speed of vehicles travelling through the village would be reduced with negligible impact on vehicle delay.

 

The investigation included a Road Safety Audit that identified the following main risks:

·         Reduced carriageway width would increase vehicle conflicts for the two way option,

·         Mitigating measures would be required for the two way option to raise driver awareness of alignment changes and to maintain an appropriate approach speed, Vehicle speeds recorded in June 2004 prior to traffic signals first being introduced found the design speed was 42 mph recorded by the entrance to the school,

·         Overlapping paths of vehicles on the narrow sections of carriageway in the two way option could result in vehicle strikes and that adequate clearance needs to be available for appropriate size vehicles during two way movements,

·         Poor provision at the traffic signals to accommodate equestrians and cyclists could result in accidents and therefore it is recommended that adequate signal timing is available to take account of their movements

·         During the development of the options key stakeholders were asked for their views. The Parish Council strongly stated their preference for a two way option, and a referendum in Colwall also supported the two way option. Representations in support of a single way traffic controlled option were received from Coca Cola, the Ledbury Area Cycle Forum and the governors of Colwall Primary School. The Coca Cola submission noted that this option would remove kerb strikes. This implies that movement within the existing highway layout is difficult and suggests that there is also potential for pedestrian conflict if large vehicles are clipping the kerb.

 

The main two options developed to provide benefits to non motorised users and the benefits / concerns can be summarised in the following table.

Option

Description

Benefit

Disadvantages

Single Way

Traffic signals to control vehicle movements across a narrow carriageway allowing the footway to be widened

Improves footway for pedestrians

Calms vehicles speeds in vicinity of bridge

Can accommodate equestrians and cyclists safely

Increased journey time for drivers

Cyclists would have to start on a steep hill

‘Urbanisation’ of rural village suggested by some

Two Way (including consideration of Parish Council proposals)

Narrowing the carriageway to nominally 6.0m –6.5m to allow the footway to be widened

Improves footway for pedestrians

Avoids marginal delay to vehicles associated with traffic signals

 

Risk of vehicle conflict due to narrow carriageway

Does not address high vehicle speeds and could result in increase

Would require traffic calming on approaches to reduce speeds to comply with prevailing speed limit

 

If Herefordshire Council allowed a two way flow of traffic knowing that there were safety concerns, and without erecting warning notices, there is always the possibility that there might be a successful claim for personal injury or damage to property should there be an accident, which could be proved to have been caused by the fact that a two way traffic flow was in operation when conditions perhaps merited a one way flow.  It therefore could be considered potentially negligent of the Council to introduce a scheme that does not take account of these concerns.

 

In summary as there are significant safety risks that have been identified in relation to the two way options as outlined above it was recommended that the single way traffic controlled proposal be adopted to ensure the safety of all road users. The detailed highway design will be is progressed to meet with the Network Rail programme for the bridge.

For further information please contact Herefordshire Council, Highways, Unit 3 Thorn Business Park, Rotherwas, Hereford, HR2 6JT, Telephone 01432 261800, email streets@herefordshire.gov.uk, website www.herefordshire.gov.uk

This sheet can also be obtained from the Colwall Parish Council website www.colwall.net and from the Herefordshire Info shop Ledbury, Colwall Public Library and a number of commercial outlets.

Weekly update reports on the progress of the bridgeworks are provided by Network Rail and posted at the site. Network Rail’s national helpline number is 08457 114141