
Colwall Green Railway Bridge
Re-opening the bridge to light traffic
As given in Report 4
Colwall Green Railway Bridge was re-opened on Friday 7 December to light
vehicles (up to 3 tonnes). The route is supported by the
internal beams to the bridge. The beams are at an angle to the highway and are
the strongest parts of the
bridge. It is for this reason that the route over the
bridge takes its S-shape course.
The Council is aware
that there have been a number of accidents on the bridge and it is taking a
number of measures to alleviate the problems of the route through a formal
audit of the route by a specialist auditor. The Council received the draft
findings of the report on 23 January and it has commenced actions to implement
the findings.
There will be
improvements to the lighting, the route (for vehicles and pedestrians) and to
signage. A timetable for the improvements is being determined and the work will
be completed as soon as possible, probably in two or three phases.
There is a separate
work programme in place to assess if there can be improvements to the advanced
signage and so maximize driver awareness of the weight restriction on the
bridge.
Completion
of the bridge assessment
On 13 December Herefordshire Councilís Cabinet agreed
that a temporary Bailey bridge could be installed over the bridge if that was
considered to be the most appropriate solution.Ý This
approval required the completion of the assessment report into the capacity of
the bridge before implementation.Ý
The work to determine the assessed capacity of the
bridge was completed at the end of December and the report formally passed to
Network Rail and Herefordshire Council on 10 January. This report has been
approved by Network Rail (Herefordshire Council were notified by letter
datedÝÝÝÝ 30 January). The assessment
found that capacity of the bridge to be 7.5 tonnes in some internal girders, 3
tonnes in others and 0 tonnes in the main girders.
Meetings were held between Herefordshire Council
and Network Rail officers on 10 January and 30 January to study the findings of
the assessment report with the objective of determining how to proceed. The
conclusion of the meetings is that work should proceed to identify viable options
for deck reconstruction.
The proposed
scheme for re-opening the bridge
The Councilís approach had been to provide, as an
interim measure, a narrow Bailey bridge to take vehicle traffic with
pedestrians on the footway of the existing bridge. This was seen as an interim
measure pending the construction of a new bridge. However, the assessed
capacity of theÝ large edge girders
supporting the footways does not allow us to proceed with this arrangement
because it has been calculated that they can only take their own weight but not
pedestrians.
It would be possible to redesign the scheme but
this will take a significant time due primarily to the need to find an
alternative pedestrian route (possibly a pedestrian bridge or a walkway
attached to the proposed Bailey bridge).
Network Rail and Herefordshire Council officers
have therefore concluded, using the results of the assessment report noted
above that, the best solution is to proceed directly to the construction of a
new bridge.
The decision to recommend a new bridge is not
related to any funding shortfall but is purely as a consequence of the findings
of the assessment report. Likewise earlier decisions were based on achieving an
early opening of the bridge and not related to funding criteria.
The assessment result does not affect the
continuation of the 3 tonne route over the bridge as an interim measure.
It is proposed that the programme for the work will
be accelerated. The following section gives the details.
Next steps
for the construction of a new bridge deck
The key to this proposal is an accelerated
programme through the purchase by Network Rail of rail closures for the
construction work.Ý There is significant
preparatory work required to ensure these closures can proceed with confidence.
It is anticipated that the work will be undertaken by Network Rail during next
year.
The next steps therefore include the following
work: a feasibility study, preparation of a preliminary programme and extent of
work, agreement of rail closure times with the train operating companies,
formal approval from Network Rail and Herefordshire Council to the programme
and extent of work, design, and construction.
It is proposed that representatives from Network
Rail and Herefordshire Council will attend a parish council meeting to explain
the proposals, the rationale behind the proposals and the timetable when this
information is developed. A substantial amount of work needs to be undertaken
and at present the details have to be developed and are incomplete. It will be
a little time before the outline is sufficiently advanced to be described with
confidence. Regular project meetings have been set up between Network Rail and
Herefordshire Council in order to progress the work as quickly as possible.
Progress
reports - If you wish to receive
forthcoming progress reports direct by e-mail please contact the council
through the routes given below.
For further
information please contact Herefordshire Council, Highways and Transportation,
Unit 3 Thorn Business Park, Rotherwas, Hereford, HR2 6JT, Telephone 01432
261800, email streets@herefordshire.gov.uk,
website www.herefordshire.gov.uk
This sheet can also
be obtained from the Colwall Parish Council website www.colwall.net and
from the Herefordshire Info shop Ledbury.