
Public meeting held on Wednesday 27 February
At a public meeting held at
Network
Rail, which owns the bridge and is responsible for its maintenance, said it
usually took three years to build a new bridge. But following negotiations at
the highest level between the company and the council, the programme has been
fast tracked to enable a new bridge to be built and opened by March 2009.
Herefordshire Council
and Network Rail confirmed that funding was available to construct the new
bridge to timetable. The meeting of 120 Colwall residents was told that the
process of appointing the right contractor for the job would begin straight
away, and would take around three months.
From June, the bridge
would be designed with the contractor and necessary approvals obtained. Work on
fabricating the new structure would begin in October to prepare for the old
bridge to be demolished in February next year and the new one constructed with
a planned opening in March 2009.
In the meantime,
Herefordshire Council said it would work with Colwall Parish Council to improve
lighting and signage for the restrictive ‘chicane’ route of the existing bridge
and reassess diversion routes.
The current chicane
system for light traffic over the bridge was defended. Although it appeared
crude it was designed to be as safe as possible. If the design width to the
carriageway was altered by even a small amount, the traffic would put
unacceptable stresses on the weaker girders within the bridge. (See below for
planned improvements to the route.)
The council stated
that it subsidises bus services in the Colwall area and is putting in extra
funds from the bridge works project to make sure that extra re-routing costs to
operators are not passed on to passengers.
It had been planned
to provide a temporary bridge over the existing bridge as an interim measure
but engineers determined, following the issue of an assessment report in
January 2008, that it would not be a satisfactory solution. Even if implemented,
a temporary bridge would have cost £1/2 million and could have resulted in the
building of a new bridge being put back in the Network Rail’s regional bridge
building programme.
Next steps
for the construction of the new bridge
The key to the proposal for an accelerated
programme is the removal of time for contingencies outside the control of
Network Rail and Herefordshire Council and a minimisation of design and
construction processes.
The key steps to the bridge replacement include the
following work: procurement of design and construction services, bridge design
and approval processes, fabrication of the new structure, installation of a
temporary footbridge, diversion of services (gas, electricity, telephone)
demolition of the existing bridge and bridge reconstruction.
Pedestrian traffic will be accommodated by the
provision of a temporary footbridge during the works. However there will be a
period when vehicular traffic will not be able to cross and hence will need to
follow the signed diversion route. This bridge closure will be minimised as
much as possible. Network Rail and Herefordshire Council will be working
together to deliver the project.
The programme does not allow for contingencies such
as environmental factors affecting the works that are outside Network Rail’s
control. The
programme for the new bridge works, as presented at the meeting, is reproduced
below:
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Description |
MAR |
APR |
MAY |
JUN |
JUL |
AUG |
SEP |
OCT |
NOV |
DEC |
JAN |
FEB |
MAR |
|
|
|
|
Procurement
Process |
|
|
|
|
|
|
|
|
|
|
|||||
|
|
Contract
Award |
|
|
|
|
|
|
|
|
|
||||||
|
|
Bridge
Design & Approval Process |
|
|
|
|
|
|
|
|
|
|
|||||
|
|
New
Structure - Fabrication |
|
|
|
|
|
|
|
|
|
|
|||||
|
|
Temporary
F/B Installed |
|
|
|
|
|
|
|
|
|
||||||
|
|
Services
Diverted |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Site
Preparations |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Main
road closures |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Site
Demobilisation |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Temporary route for light traffic
The Council is aware
of residents’ concerns for the current route over the bridge. Following a
formal audit a number of amendments have been identified. These will include
the following:
Phase 1 (by mid April)
Install “cats eyes” to the edge of the carriageway, removal of overhanging
branches, apply road markings and hatching, additional signing, improvements to
the pedestrian route, changes to the fencing, installation of chevron markings.
Phase two (within 4
months due to the need for approvals from other organisations) street lighting,
improvements to the traffic signals and additional signing.
Progress reports - If you wish to receive forthcoming progress reports
direct by e-mail please contact the council through the routes given below. The
next progress report will be issued in April.
For further
information please contact Herefordshire Council, Highways and Transportation,
Unit 3 Thorn Business Park, Rotherwas, Hereford, HR2 6JT, Telephone 01432
261800, email streets@herefordshire.gov.uk,
website www.herefordshire.gov.uk
This sheet can also
be obtained from the Colwall Parish Council website www.colwall.net and
from the Herefordshire Info shop Ledbury.